November 8, 2021, Update #6

November 8, 2021 Master Facility Update #06

Below is an overview of construction that is happening at Cheyenne Regional West for this upcoming week.

Highlights:

  1. A crane will be in operation on 24th street today and tomorrow.
  2. Elevator B2 will not open on the 3rd floor WEST side for the remainder of this month.

#1

 

What is happening?

West Building: 24th Street Closures and Sidewalk Closures

 

Access to dock, North Parking Garage, and Cancer Center will be available

 

When is this happening?

November 8 (Monday) – See Green – Access to Cancer Center and parking garage from Evans Ave.

November 9 (Tuesday) – See Blue – Access to Cancer Center and parking garage from Warren Ave.

Why is this happening?

Who to call with questions?

Jackie Van Cleave, extension 7785

Candis Pickard, extension 7890

Kelly Archer, extension 6487

 

#2

 

What is happening?

Elevator B2 – the west side door will not open on the 3rd floor (3-1 / 1968 building side). Contractor will be working in the hall and the containment wall will be blocking the elevator door.

Where is this happening?

3rd Floor 3-1 (1968) / Patient Tower

 

When is this happening?

Nov 8 – Dec 2

Why is this happening?

Master Facility Plan 

Who to call with questions?

Jackie Van Cleave, extension 7785

Kelly Archer, extension 6487