Below is an overview of construction that is happening at Cheyenne Regional West for the upcoming week(s).
Highlights:
3rd floor hallway to Cancer Center bridge by Central Supply will be temporarily re-routed through the CS space starting March 24th
B1 elevator is nearly complete. Inspections are being held this week and we will open once we have occupancy notice from the State
Evans avenue will be closed on April 5th to accommodate a concrete pump truck
4th floor construction update
#1
What is happening?
Temporary re-route of the hallway in 3-1 North which goes to CS and leads to the Cancer Center bridge (area in red below)
The temporary hallway will be located through Central Supply to allow patients and employees access to the Cancer Center bridge. Please see the yellow temp hallway in picture below. The green line represents how access will be from either side.
Where is this happening?
When is this happening?
March 24 through end of April 2022
Why is this happening?
Master Facility Plan – Plumbing work
Who to call with questions?
Jackie Van Cleave, extension 7785Glenn Shenefelt, 287-1477
Phil Villarreal, extension 7979
Kelly Archer, extension 6487
#2
What is happening?
A concrete pump truck will be parked on Evans Ave. which will require street closures.
Where is this happening?
Evans Street will be shut down between 22nd and 24th streets
23rd Street will be shut down between Van Lennen Ave. and Evans Ave. streets
When is this happening?
April 5th – all day
Why is this happening?
Master Facility Plan – Concrete Pump truck to supply concrete up to the 9th floor roof for a future roof top unit
Who to call with questions?
Jackie Van Cleave, extension 7785Glenn Shenefelt, 287-1477
Phil Villarreal, extension 7979
Kelly Archer, extension 6487
#3
What is happening?
We are nearly complete with the refurbishment of B1 elevator car. Inspections are occurring this week and we will open it back up as soon as we have the State occupancy letter in hand.
Where is this happening?
When is this happening?
Week of March 21, 2022.
Why is this happening?
The elevators need to be refurbished as they have not been since the building was built in 2002. They are almost 20 years old.
Who to call with questions?
Jackie Van Cleave — x 7785Phil Villarreal — x 2297
Candis Pickard — x 7890
Kelly Archer– x 6487
#4
What is happening?
Sawing, drilling, “thuds”, and vibration on the 4th floor, mostly in the 68 building, some in the patient tower.
Thuds, drilling, and impact noises will be ongoing in the 68 building for the next few weeks as the contractor is installing pipes and electrical conduit.
Contractor is working on finishing drywall in the patient tower and looking to start drywall hanging in the 68 building next week.
Contractor has moved out of 3-2 (woohoo!) and if you haven’t noticed, has mobilized in 3-1. They will continue working on the third floor of the 68 building through April.
Where is this happening?
4th floor, patient tower and 68 building.
When is this happening?
Ongoing
Why is this happening?
As part of the Master Facility Plan, we are remodeling the 4th floor 68 building and 4thfloor patient tower to accommodate a new Mother Baby Unit. This construction will be ongoing until fall of 2022.
Who to call with questions?
Jackie Van Cleave, extension 7785Glenn Shenefelt – x2647